With the bulk of the civil works at Blacktoft Nursery complete, the electrical and mechanical hardware can now be installed. This transition was dramatically marked by the arrival and installation of the EWT 500 kW turbine, which took place a few days ago.
Due to its size, the EWT 500 kW turbine negotiated the newly created access tracks in a fleet of long vehicles, with each vehicle carrying individual components of the turbine. The three wind turbine blades, each measuring 27 m in length, arrived on one delivery vehicle. The turbine tower totalling 75 m in length arrived on three separate vehicles.

Wind turbine blades en route to site.
In tandem with the turbine delivery, all of the required lifting equipment, including a 750 tonne crane, arrived on site too. Temporary trackway and a temporary bridge were used to cross local farmland, with careful management required to ensure safe setbacks from electricity cables.
The turbine components were not ground based for long. Once all equipment and hardware had arrived on site, the erection of the wind turbine commenced immediately. Despite several pauses due to strong winds, the turbine erection took only a couple of days.

EWT 500 kW turbine securely installed within sunken foundation.
Are you considering a wind turbine project?
Renewables First are an experienced wind consultant and have a full project capability, from initial feasibility study through to wind consenting and installation.
The first step to develop any wind power site is to conduct a full Wind Turbine Feasibility Study.
If you are interested in installing a wind turbine, the first step is to Contact us to discuss your requirements and to complete a Wind Turbine Feasibility Study.