The Hydro and Wind Company Securing a clean energy future, profitably

Wind turbine commissioning at Blacktoft Nursery

Wind turbine commissioning at Blacktoft Nursery
Blacktoft Wind turbine Commissioning - Renewables First

Blacktoft wind turbine commissioning.

Following the turbine installation in November, December 2014 saw the final technical stages completed: energisation and wind turbine commissioning.  These are the final checks before the system can be handed over to the client.

Energisation is the technical process by which the turbine is connected to the local electricity grid network and made live. From this point on, the nursery can then both export and import electricity to/from the grid as required. Wind turbine commissioning involves a series of technical checks to ensure that the system is performing properly.

Now that the turbine is fully operational and grid-connected, it can fulfil its role as a generator of electricity from a renewable and abundant resource – the wind.

The Blacktoft Nursery project is now entering the final stages of development. This will focus mainly on landscaping, restoration and making good of the site.

Several months on…

Below is a selection of images taken in early spring, four months later.

Approaching…

Renewables First - Blacktoft Nursery wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Getting closer…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

From the base looking up…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Looking around…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Wind turbine commissioning - Renewables First

Blacktoft Nursery EWT 500 kW wind turbine

Wind turbine commissioning - Renewables First

Blacktoft Nursery EWT 500 kW wind turbine

Are you considering a wind turbine project?

Renewables First are an experienced wind consultant and have a full project capability, from initial feasibility study through to wind consenting and installation.

The first step to develop any wind power site is to conduct a full Wind Turbine Feasibility Study.

If you are interested in installing a wind turbine, the first step is to Contact us to discuss your requirements and to complete a Wind Turbine Feasibility Study.